TUSAS CEO just gave an interview. A summary:
Anka:
- 5 are built per month. At the moment, Turkey has a problem of not being able to fulfill orders.
- Anka has been exported to 12 countries so far.
Hurkus:
- We exported HÜRKUŞ to 2 countries, and a third country is on the way.
- We have a target of 2 units per month.
- We produced 15 HÜRKUŞs, 5 of which we sold. We will sell the rest and continue production.
Atak-2 (T929)
- The engine of the ATAK-2 will start in a few days.
- It will make its first flight this month.
- We will deliver three to the Turkish Land Forces in 2025.
- The engines of the ATAK-2 come from Ukraine.
- We designed the transmission, and Alp Aviation made the shaft.
- It'll have 1.5 ton payload.
Gokbey (T625)
- Today, we installed two engines (TS1400) produced by TEI on GÖKBEY and started it up.
- Now it will soon fly with these engines.
Utility Helicopter 10 tons (T925):
- T925 The navy version of the Utility Helicopter is being developed.
- Design changes such as folding rotor, tail and sea-resistant fuselage will be made for use in the navy.
- T925's naval version will be deployed on TCG ANADOLU.
- The 10-ton utility helicopter will make its first flight next year, with the first delivery scheduled for 2026.
ANKA-III:
- ANKA-III is currently performing taxi tests.
- Maiden flight will be in the next couple of days.
TF-X/MMU:
- The National Combat Aircraft will be the fastest completed aircraft in the world. We will fly it with our own engine in 2028.
- Preliminary work on the engine of the MMU has been ongoing at TRMOTOR for three years. We have come to a certain point.
- It'll be able to fly supersonic for several hours.
- There will be antennas on the rear overhang between the engines and TF-X will monitor/listen everywhere.
Miscellaneous:
- TAI has over 14000 employees currently. (will reach 16000 by the end of the year)
- TAI has 14 billion dollars of pending business, including everything.
- 1.3 billion dollars was signed with foreign countries in the last 3-4 months.
- We have orders worth 2 billion dollars awaiting delivery.
- The GÖKTÜRK-Y satellite we are currently building is 100% domestic. The most important part is its camera.
- TÜRKSAT 6-A is almost finished. We are conducting the final tests. It will be put into orbit in the coming months.
- Turkey is one of the 7 countries in the world that can build satellites.
Also a new air launched drone with (V)LO characteristics under the wings of the ANKA-3?