Judging by the size and completion level of that module, it seems closer to QE kind of construction. As opposed to Ford class construction or Dalian's cv17 construction which used smaller modules to build up the whole ship.
For QE:
First large module was placed in its place 3 years before launch. Commissioning then took another 3.5 years after launch.
For Ford carrier:
Took 4 years from first part being laid down to launch. Then another 2.5 years to commission.
Carrier 002/ cv17
Took 3.5 years from first part being laid down to launch.
Liaoning carrier
Took a year or year and a half to commission.