This is kinda sad. First the Russians are going to be four years late on India's aircraft carrier, and India's own indigneous aircraft carrier program has hit snags as well.
After Gorshkov, another Navy project hit by delay
NEW DELHI: The bad news for Navy shows no sign of stopping. The country's most ambitious ship-building project, construction of a 37,500-tonne indigenous aircraft carrier (IAC) at Cochin shipyard, is running way behind schedule. Sources said current projections show IAC will be ready for delivery to Navy earliest by 2015, after completion of construction and trials, instead of the earlier date of 2011-2012.
The IAC project, cleared by the government in January 2003 at a cost of Rs 3,261 crore after several years of dilly-dallying, is lagging behind on "almost all fronts".
"First, there was a big problem in getting 20,000 tonnes of special quality steel for it till SAIL stepped in. Then, there was a huge delay in procurement of bulb bars. Once these was sorted out, other problems crept in," a source said.
"The detailed designs and pre-production work also took a lot of time. As per revised plans, the keel of the warship was to be laid in October 2007 but this has been postponed by at least an year now. Consequently, the project cost will also go up substantially," he added.
All this will add to the woes of Navy, already grappling with huge delays in some big-ticket projects. The induction of the decommissioned Russian aircraft carrier Admiral Gorshkov, for instance, will not be possible before 2010. Rechristened INS Vikramaditya, this 44,570-tonne carrier was supposed to be operationally ready by August 2008, as per the Rs 6,900 crore package deal signed with Russia in January 2004.
Then, of course, there are slippages in the gigantic Rs 18,798 crore project to construct six Scorpene submarines at Mazagon Docks, slated for delivery between 2012 and 2017.
In the IAC project, the government has even signed two contracts worth 28 million Euros with Italian firm Fincantieri for design, integration, installation and commissioning of the IAC's propulsion system, apart from consultancy in detailed engineering and documentation.
"But despite the steel being cut at the Cochin shipyard in April 2005, the ship construction began only in November 2006," said the source.
To be charitable, one can argue this is the first time India is building an aircraft carrier, which has been the preserve of only US, UK, Russia and France so far.
But almost all defence projects of India suffer from huge time and cost overruns, underlining the lack of proper planning. Though the Navy has projected the need for three aircraft carriers to emerge as the most potent force in the region, it is making do with only one, the 50-year-old INS Viraat, at the moment. Be that as it may, once it is ready, the 252-metre-long IAC will have two runways with ski-jumps and a landing strip with three arrester wires, with the flight deck being around 2.5 acres.
With 160 officers and 1,400 sailors, the ship will be able to carry 12 MiG-29Ks, eight Tejas Light Combat Aircraft and 10 helicopters. Powered by four LM2500 gas turbines generating 80 MW, the carrier will be able to attain a maximum speed of 28 knots and be operationally deployed for 45 days at a stretch.
The overhaul of a Russian-made aircraft carrier sold to India under a 2004 contract will be delayed indefinitely due to insufficient financing and poor management of the project, a Russian daily said Wednesday.
The contract to deliver the Admiral Gorshkov aircraft carrier to India, which state-run arms exporter Rosoboronexport signed with the Indian Navy in January 2004, covers the modernization of the ship and equipping it with modern weaponry, including the MiG-29K Fulcrum aircraft and Ka-27 Helix-A and Ka-31 Helix-B anti-submarine helicopters.
The ship is undergoing modernization work at the Sevmash shipyard in Severodvinsk, in northern Russia, but its completion could be delayed for at least another four years, according to some reports.
"The aircraft carrier is being overhauled at the shipyard, but, unfortunately, the funds allocated for the work under the contract are not sufficient and we will have a hard time to meet the schedule," the Izvestia newspaper cited Eduard Borisov, the acting director of Sevmash, as saying.
"We are practically building a new ship using an old hull and changing everything else," Borisov said, adding that the company's management had earlier made an incorrect assessment of the modernization cost.
A high ranking source in the defense industry told RIA Novosti that the company's officials had underestimated the projected overhaul budget by at least 60-70% but had denied their mistakes for a long time.
He said the work already done on the Admiral Gorshkov could be compared to the construction of two destroyers.
"It would have been much easier to start the construction of an aircraft carrier from scratch than to modernize the old one," the source said.
Former director of the Sevmash shipyard, Vladimir Pastukhov, has been recently fired over his poor management of the project and some media reports suggested that prosecutors had been investigating a possible fraud case over mismanagement of funds by Sevmash officials.
Izvestia said Nikolai Kalistratov, the general director of the neighboring Zvyozdochka shipyard, could be appointed as the new head of Sevmash in the next few weeks.
The $1.5-billion Admiral Gorshkov sale is one of Russia's largest individual military deals with India. The two countries are currently working on military contracts worth $10 billion.
After joining the Indian Navy, the 45,000-ton aircraft carrier will be renamed the INS Vikramaditya and could replace the outdated INS Viraat, a Centaur-class aircraft carrier, which India purchased from Britain in 1986
Shipbuilder Head Fired Over Delay
Combined Reports Vladimir Pastukhov has been dismissed as general director of Sevmash shipyard, the country's largest shipbuilding enterprise, over the company's failure to fulfill a $1.5 billion contract to modernize an aircraft carrier sold to India in 2004, Interfax reported Wednesday.
"The reason for Pastukhov's dismissal is the failure to carry out the contract to re-equip and modernize the aircraft carrier on behalf of the Indian navy," a source at Sevmash told Interfax. "The contract is delayed for three years. ... The realistic date ... is now 2011."
Under the contract, Sevmash shipyard was due by 2008 to upgrade and re-equip the ship, built in 1987, to combine the power of a missile cruiser and capabilities of an aircraft carrier.
Indian media and officials have said the ship, with a squadron of MIG-29 jet fighters on board, would considerably enhance the firepower of the Indian navy and bring nuclear rival China within range. India is the only country in South Asia that has an aircraft carrier, an issue of concern for some of its smaller neighbors.
Interfax quoted the Sevmash source as saying that miscalculating the amount of work needed to renovate the ship had led to problems.
"After a more detailed examination was conducted, it became clear that the ship's technological condition is awful and that money allocated for the renovation is not enough," he said.
The source at Sevmash also said the most likely replacement for Pastukhov would be Nikolai Kalistratov, who is currently general director of Zvyozdochka ship-repair plant, Interfax reported.
After Gorshkov, another Navy project hit by delay
NEW DELHI: The bad news for Navy shows no sign of stopping. The country's most ambitious ship-building project, construction of a 37,500-tonne indigenous aircraft carrier (IAC) at Cochin shipyard, is running way behind schedule. Sources said current projections show IAC will be ready for delivery to Navy earliest by 2015, after completion of construction and trials, instead of the earlier date of 2011-2012.
The IAC project, cleared by the government in January 2003 at a cost of Rs 3,261 crore after several years of dilly-dallying, is lagging behind on "almost all fronts".
"First, there was a big problem in getting 20,000 tonnes of special quality steel for it till SAIL stepped in. Then, there was a huge delay in procurement of bulb bars. Once these was sorted out, other problems crept in," a source said.
"The detailed designs and pre-production work also took a lot of time. As per revised plans, the keel of the warship was to be laid in October 2007 but this has been postponed by at least an year now. Consequently, the project cost will also go up substantially," he added.
All this will add to the woes of Navy, already grappling with huge delays in some big-ticket projects. The induction of the decommissioned Russian aircraft carrier Admiral Gorshkov, for instance, will not be possible before 2010. Rechristened INS Vikramaditya, this 44,570-tonne carrier was supposed to be operationally ready by August 2008, as per the Rs 6,900 crore package deal signed with Russia in January 2004.
Then, of course, there are slippages in the gigantic Rs 18,798 crore project to construct six Scorpene submarines at Mazagon Docks, slated for delivery between 2012 and 2017.
In the IAC project, the government has even signed two contracts worth 28 million Euros with Italian firm Fincantieri for design, integration, installation and commissioning of the IAC's propulsion system, apart from consultancy in detailed engineering and documentation.
"But despite the steel being cut at the Cochin shipyard in April 2005, the ship construction began only in November 2006," said the source.
To be charitable, one can argue this is the first time India is building an aircraft carrier, which has been the preserve of only US, UK, Russia and France so far.
But almost all defence projects of India suffer from huge time and cost overruns, underlining the lack of proper planning. Though the Navy has projected the need for three aircraft carriers to emerge as the most potent force in the region, it is making do with only one, the 50-year-old INS Viraat, at the moment. Be that as it may, once it is ready, the 252-metre-long IAC will have two runways with ski-jumps and a landing strip with three arrester wires, with the flight deck being around 2.5 acres.
With 160 officers and 1,400 sailors, the ship will be able to carry 12 MiG-29Ks, eight Tejas Light Combat Aircraft and 10 helicopters. Powered by four LM2500 gas turbines generating 80 MW, the carrier will be able to attain a maximum speed of 28 knots and be operationally deployed for 45 days at a stretch.
The overhaul of a Russian-made aircraft carrier sold to India under a 2004 contract will be delayed indefinitely due to insufficient financing and poor management of the project, a Russian daily said Wednesday.
The contract to deliver the Admiral Gorshkov aircraft carrier to India, which state-run arms exporter Rosoboronexport signed with the Indian Navy in January 2004, covers the modernization of the ship and equipping it with modern weaponry, including the MiG-29K Fulcrum aircraft and Ka-27 Helix-A and Ka-31 Helix-B anti-submarine helicopters.
The ship is undergoing modernization work at the Sevmash shipyard in Severodvinsk, in northern Russia, but its completion could be delayed for at least another four years, according to some reports.
"The aircraft carrier is being overhauled at the shipyard, but, unfortunately, the funds allocated for the work under the contract are not sufficient and we will have a hard time to meet the schedule," the Izvestia newspaper cited Eduard Borisov, the acting director of Sevmash, as saying.
"We are practically building a new ship using an old hull and changing everything else," Borisov said, adding that the company's management had earlier made an incorrect assessment of the modernization cost.
A high ranking source in the defense industry told RIA Novosti that the company's officials had underestimated the projected overhaul budget by at least 60-70% but had denied their mistakes for a long time.
He said the work already done on the Admiral Gorshkov could be compared to the construction of two destroyers.
"It would have been much easier to start the construction of an aircraft carrier from scratch than to modernize the old one," the source said.
Former director of the Sevmash shipyard, Vladimir Pastukhov, has been recently fired over his poor management of the project and some media reports suggested that prosecutors had been investigating a possible fraud case over mismanagement of funds by Sevmash officials.
Izvestia said Nikolai Kalistratov, the general director of the neighboring Zvyozdochka shipyard, could be appointed as the new head of Sevmash in the next few weeks.
The $1.5-billion Admiral Gorshkov sale is one of Russia's largest individual military deals with India. The two countries are currently working on military contracts worth $10 billion.
After joining the Indian Navy, the 45,000-ton aircraft carrier will be renamed the INS Vikramaditya and could replace the outdated INS Viraat, a Centaur-class aircraft carrier, which India purchased from Britain in 1986
Shipbuilder Head Fired Over Delay
Combined Reports Vladimir Pastukhov has been dismissed as general director of Sevmash shipyard, the country's largest shipbuilding enterprise, over the company's failure to fulfill a $1.5 billion contract to modernize an aircraft carrier sold to India in 2004, Interfax reported Wednesday.
"The reason for Pastukhov's dismissal is the failure to carry out the contract to re-equip and modernize the aircraft carrier on behalf of the Indian navy," a source at Sevmash told Interfax. "The contract is delayed for three years. ... The realistic date ... is now 2011."
Under the contract, Sevmash shipyard was due by 2008 to upgrade and re-equip the ship, built in 1987, to combine the power of a missile cruiser and capabilities of an aircraft carrier.
Indian media and officials have said the ship, with a squadron of MIG-29 jet fighters on board, would considerably enhance the firepower of the Indian navy and bring nuclear rival China within range. India is the only country in South Asia that has an aircraft carrier, an issue of concern for some of its smaller neighbors.
Interfax quoted the Sevmash source as saying that miscalculating the amount of work needed to renovate the ship had led to problems.
"After a more detailed examination was conducted, it became clear that the ship's technological condition is awful and that money allocated for the renovation is not enough," he said.
The source at Sevmash also said the most likely replacement for Pastukhov would be Nikolai Kalistratov, who is currently general director of Zvyozdochka ship-repair plant, Interfax reported.