Long March9 first launch in 8 to 10 years and prototype has already been built.
Short-duration hot fire tests of all 3-stage engines have been conducted
Didn't notice your post until now.
I must say that this is a surprise. Long Lehao is playing us.
From his wording, engines of all 3 stages have conducted full system test. However we don't know exactly which engines are they. This is what I gathered from open reports. Green means full system hot test, Blue means half system (turbine, GG combined) test. A full YF90 was assembled in 2021 but never heard it conducting full test.
CZ-9 | 2011 | 2021 | 20220917 | 2022 |
1st stage | YF130 | YF135 | 240t LOX/Kerosene | 200t Methene |
2nd stage | YF90 | 120t LOX/LH | 120t LOX/LH | 120t LOX/LH |
3rd stage | YF79 | 120t LOX/LH | 120t LOX/LH | 120t LOX/LH |
Two possibilities
- Long Lehao was talking about 2011 version of CZ-9 if CASC did not withheld information from the public regarding engine tests.
- There are more engines completed full test than CASC has shared with the public.