1000 MW Quaid e Azam Solar Power Plant.
In phase-I,100MW were commissioned in May 2015.
In phase-II,300MW were connected to the grid in June 2016
In phase-III,the working on 600MW is already in process & is expected to be fully completed by the end of 2018
The Quaid e Azam Solar Park is a photovoltaic power station under construction in ,named in the honor of Quaid e Azam Muhammad Ali Jinnah.Currently the transmission line has a capacity of up to 400 MW.
Pakistan’s first-ever solar generation project was formally inaugurated at the Quaid e Azam Solar Park on 5th May 2015..