With how modular shipbuilding is these days wouldn't they only need to design the reactor sections and import the 003 schematic for the rest of the carrier to save on time? If they needed to further modify from there the 003 design is there as a baseline so you don't have to start from scratch.
Exactly. Design will not be from zero. In fact 003 must have been designed to scale to 004 in mind. Even start from actual zero like 002 didnt go that slow.
From what I have experienced, no, no and no. Its a recipe for disaster going this way. If you haven't got the reactor section locked down, and especially if you don't have any previous experience, then usually everything that can go wrong will go wrong. Your heat and mass balance, utility and electric load etc will cause extensive modifications that will take even more time. This is not mentioning all the unknown unknowns that tend to creep in. This is why nearly all fast tracked engineering of this type fails.With how modular shipbuilding is these days wouldn't they only need to design the reactor sections and import the 003 schematic for the rest of the carrier to save on time? If they needed to further modify from there the 003 design is there as a baseline so you don't have to start from scratch.
I highly doubt that IF though. The difference between a CVN and conventional CV is the reactor compartment and how you run the steam pipes to the turbine room. The hull structure will be designed around the pre-determined dimension of that reactor compartment. The impact to rest of the hull is not a big deal IMO.If you start designing the ship in 2023 then it won't enter service for another decade. Advocating for a decade-long pause in PLAN's carrier inventory in an increasingly sensitive strategic environment seems unwise.
I have previously suggested that I think PLAN should run off an additional three 003-type carriers at rapid (~3yr) cadence to achieve a credible 6-carrier force by 2035 at relatively low cost. If that were actually going to occur then pre-production work for carrier #4 would already be underway and certain long-lead items for carriers #5 and #6 might have been ordered (or at least "flagged") too. This is merely to illustrate my sense of the timelines involved, what PLAN actually chooses to do is obviously its own affair.
Your assumption is that the dimension of the reactor is not settled. That is only if you don't determine the dimension from the very beginning. However, my thought is that the dimension of the reactor is a design specification of the reactor which is not allowed to be changed (enlarged), nor physically possible to enlarge. It is locked in the beginning and not allowed to be changed afterwards.From what I have experienced, no, no and no. Its a recipe for disaster going this way. If you haven't got the reactor section locked down, and especially if you don't have any previous experience, then usually everything that can go wrong will go wrong. Your heat and mass balance, utility and electric load etc will cause extensive modifications that will take even more time. This is not mentioning all the unknown unknowns that tend to creep in. This is why nearly all fast tracked engineering of this type fails.
Plus the modular ship building works better the more mature the design. You can have a concept on how many modules etc, but everything inside that module at that stage is just a white box. Only after you get to 30 or 60% review then you lock down your module configuration and interface points, and it becomes something tangible to plan and build.
To be sure, there is definitely time and cost savings in there because the other subsystems are mature, and kind of already there, but it won't be nearly as much as people think if the key piece is being designed concurrently and any major change in it will cause significant knock on effects.
Only about the bold texts.If I remember correctly, the redesign of 003 from the original steam catapult to EMALS catapult took more than 1 year, refering to slayerhuahua in CJDBY. Thus for a complete ship design work, 3 to 5 years would be quite normal. I would not be surprise if work for 004 starts in 2016 or 2017, steel cutting in 2021 or 2022, and recognisable modules appearing in 2023 or 2024.
I highly doubt that IF though. The difference between a CVN and conventional CV is the reactor compartment and how you run the steam pipes to the turbine room. The hull structure will be designed around the pre-determined dimension of that reactor compartment. The impact to rest of the hull is not a big deal IMO.
This means that PLAN could have been designing their CVN in parallel to 003 many years ago.
Reactor dimension is just 1 part of the puzzle. Once the dimension and layout is locked, there is the problem that more of the work is in the changing utilities / cooling / E&I demand, as well as the new pipe / cable tray runs etc. E.g. if you design asked for 150mm tray, so you allowed for 200mm tray, but the mature design needed 250mm tray cause you have a few more cables to run, then its not as simple as just bumping it to 250, you got run the clash checks through the whole lot, and reroute if needed. Now do that for every subsystem. (Maybe ~10,000 which any link to the reactor)Your assumption is that the dimension of the reactor is not settled. That is only if you don't determine the dimension from the very beginning. However, my thought is that the dimension of the reactor is a design specification of the reactor which is not allowed to be changed (enlarged), nor physically possible to enlarge. It is locked in the beginning and not allowed to be changed afterwards.
It is like I ask the engineers to design a sedan, the size of the engine is therefor determined. The guy will design the chassis and engine compartment in the fix size, the engine guy will do whatever necessary to fit the engine in it. Even if the engine guy has some difficulty, it is not the chassis to be changed.
Just wanted to ask why you reckon these two in particular would potentially be in the cards for the eventual CVN, when these features aren't -[snip]
But we aren't just talking about going from a "conventional CV" to a "CVN". It is more accurate to say that they are going from "conventionally powered 003" to "nuclear powered 004".
That is to say, I think we should all expect 004 to have some significant differences and improvements over 003 (even if 004 is derived from 003), which would require substantial time for redesign/expansion:
- adding another catapult on the waist (for 4 catapults rather than 3)
- slimming down the size of the island and perhaps repositioning it to the rear
- redesigned flight deck including lengthening of the overall flight deck and ship length (which requires lengthening of the overall hull), and widening parts of the flight deck too, for better deck handling
- likely adding another elevator to the ship, namely on the port/aft position
And of course, all of the modifications in relation to adding nuclear propulsion:
- replacing the conventional steam turbines with nuclear propulsion
- electrical generation overhaul associated with said nuclear propulsion
- vents and piping modifications/removals
- redesign (or expansion) of ship's aviation fuel capacity
.... all of the above, for a notional 004 derived from 003, is not something that I can see take less than 3-4 years.
Just wanted to ask why you reckon these two in particular would potentially be in the cards for the eventual CVN, when these features aren't -
1) exclusive to whether the boat is nuclear or not, of course; and
2) necessarily beneficial to the PLAN's particular modus operandi on carrier operations, in contrast to that of the USN, esp. when the PLAN could've likewise opted for 4 cats and 3 lifts on 003 in the first place yet they had elected not to anyway?