“The focus of this MACC will be the construction of a new proposed Multi-Mission Dry Dock at PSNS & IMF, located at Naval Base Kitsap (NBK) Bremerton, Washington,” the Sources Sought notice said. Located within the existing Dry Dock 3 and Piers 6 and 7, the project includes “dry dock drainage, dewatering, and flooding systems; a caisson; roadways and rail networks; portal crane track; access and egress elements; mechanical, electrical, and communications systems; support buildings; and utility routing tunnels. The proposed project also includes demolition of facilities and utilities.”
The Navy expects the first task order to include dredging, as well as work on piers, buildings and utilities. The second task order will see demolition of Dry Dock 3 and construction of the multi-mission dry dock. Task order three will provide infrastructure, such as electrical substations, utility tunnels and building crane rails. Task order four will be for the dock caisson.